The awarding of up to £900 million worth of enabling contracts for HS2 will be delayed by two months, it has been announced.

Whilst bidders were expecting to receive feedback by August, it became apparently in July that September had become a more realistic target. Updates in the construction press just this week have since revised that estimate to October.

A genuine revolution in the nation’s railways and a multi-billion pound project, this far reaching development will be divided up into three regions – North, Central and South – with the finished network running between Birmingham and London.

If the award of the enabling works has been delayed by two months, will this push back the award of the £11.8 billion civils packages that is currently expected in the Spring of 2017? Only time will tell.

For a complete list of those joint ventures bidding for the enabling works, please see below…


North – Lot 3

  • BBV JV made up of Vinci Construction Grand Projects, Vinci Construction UK, Vinci Construction Terrassement and Balfour Beatty
  • CEK JV made up of Eiffage Travaux Publics, Kier and Carillion
  • Momentum Infrastructure made up of Dragados, Hochtief and Galliford Try
  • LM made up of J Murphy & Sons and Laing O’Rourke
  • Morgan Sindall / Bam / Ferrovial JV

 Central – Lot 2

  • Align JV made up of Volker Fitzpatrick, Morrison Utility Services, Sir Robert McAlpine and Bouygues Travaux Publics
  • BBV JV made up of Vinci Construction Grand Projects, Vinci Construction UK, Vinci Construction Terrassement and Balfour Beatty
  • CEK JV made up of Eiffage Travaux Publics, Kier and Carillion
  • LM made up of J Murphy & Sons and Laing O’Rourke
  • Morgan Sindall / Bam / Ferrovial JV

South – Lot 1

  • BBV JV made up of Vinci Construction Grand Projects, Vinci Construction UK, Vinci Construction Terrassement and Balfour Beatty
  • CEK JV made up of Eiffage Travaux Publics, Kier and Carillion
  • Costain Skanska JV
  • LM made up of J Murphy & Sons and Laing O’Rourke
  • Morgan Sindall / Bam / Ferrovial JV

More City Surveys Group News & Press...


More City Surveys Group News & Press...